|
From Speakupwny.com Development On Monday, March 17th, the Lancaster Town Board approved an amended plat map for Cross Creek Subdivision. The Town approved the original map cover in January. That map outlined a 264 single-family homes subdivision, located along Pleasantview Drive and Stony Road. Flooding Continues to Hamper Sewer Construction at Cross Creek Site Recent rain, snow, and snow melt exacerbated continuing construction problems of the sewer installation at the Cross Creek site. Construction has been virtually halted since the site flooded in mid-February and subsequently froze over. February 19th Flooding The site has been plagued with problems since construction began. On November 26th, rains inundated the site and breached silt fencing erected to protect it. On December 3rd, the DEC issued a stop work order. That same day, a representative of the Developer told the Lancaster Town Board that no such order was issued. As of today, fines have not been levied for the violation. The Developer took steps to reinforce the barrier protecting the site. On December 11th, rain and snow caused water levels to rise again. The rising waters breached the reinforced barrier. The Developer took further steps to strengthen the barrier. The barrier was breached again on December 29th, by rain and snowmelt. Early in January of 2007 the Lancaster Town Board told residents that the DEC felt the developer had a proper soil stabilization program in place and they were ready to proceed with the sewer installation. The first week in February, unstable weather caused flooding which led to further sediment discharge. The DEC cited the developer for further violations on February 5th. On February 6th, heavy rains and snowmelt again flooded the site. The problems worsened this week. Water backed up south of the construction site. ![]() Water Backed up Behind Worksite The backed-up water is running around the worksite and seeping back into the creek around the retaining walls. ![]() Water Seeping into Creek around Retaining Wall The original intent of the project was to install the sewer in the winter, while the ground was frozen. The planners were apparently unaware of the fact that this area is part of the creek and is usually covered with ice and water from early winter until late spring. To See Videos from the Town Board Meeting, more Pictures of the Flooded Worksite, and See What Our Readers Think, CLICK HERE © Copyright 2003 by Speakupwny.com |


